Florida 90-Day Claim of Lien • Fla. Stat. § 713.08

Haven't Been Paid on a Florida Job? File a Construction Lien Online.

When a property owner or general contractor refuses to pay for completed labor or delivered materials, a recorded Florida Claim of Lien secures your unpaid balance directly against the real property.

Start My Florida Claim of LienNeed a 45-Day Notice to Owner Instead? →

Key Florida Claim of Lien Deadlines

  • 90 Days to Record: Must be recorded in the county where the property is located within 90 calendar days of your last day of furnishing labor or materials.
  • 15 Days to Serve Owner: A copy of the recorded Claim of Lien must be served on the property owner within 15 days of recording.
  • 1 Year to Enforce: A Florida Claim of Lien remains valid for 1 year from recording (unless shortened by a Notice of Contest of Lien).